Braasch Avenue Reconstruction 1st - 5th Streets

Project Description

Braasch Avenue from 1st Street to 5th Street is beyond its usable life, showing extensive cracking and deterioration due to age. The reconstruction project will address deteriorating infrastructure and drainage issues through street, drainage, and utility improvements.

The project is partially funded through funds from the Community Development Block Grant (CDBG) of the Nebraska Department of Economic Development. 

Project Schedule

Construction on Braasch Avenue is set to begin in April 2020 and will last through the remainder of the construction season. Final landscaping items may carry construction into the spring of 2021. 

Project Updates

May 7, 2020 - Braasch Reconstruction Project to Begin May 18, 2020. Read about it here...

April 3, 2020 - Braasch Avenue Reconstruction Project to Delay Start Date One Month. Read about it here... 

Project Improvements and Additional Information

Braasch Ave Need for Improvements Braasch Ave Planned Improvements Front Braasch Ave Planned Improvements Back

Project Phasing

Braasch Ave Project Phasing