Engineering

Take a look at the grant application HERE

Project Overview:

The City of Norfolk respectfully submits a request for funding in the amount of $2,086,411 under the Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant Program for the Local Intermodal Network Connection (LINC) Norfolk planning project. The LINC Norfolk planning project will provide a 60% design for a 4.8-mile multi-modal path and other necessary infrastructure to accommodate the 10’ wide path. The path will provide an additional safe, accessible route for the active transportation network in the community and will connect Skyview Park, from the northwest area of town, to the Cowboy Trailhead and Ta-Ha-Zouka Park in the southeast area of town, passing through the heart of Norfolk to provide a vital connection to the historically disadvantaged areas of town. The design will include enhanced landscaping, trees, street and trail lighting, trail signage, and new curb ramps at all intersections. 

Project Schedule:

Project Funding:

This project is being funded by through a planning grant awarded to the City by the US Department of Transportation's RAISE (Rebuilding American Infrastructure with Sustainability and Equity) grant program. The RAISE grant program was established under the American Recovery and Reinvestment Act of 2009 and operated under annual appropriations acts until authorized in November 2021.  The grant program has recently been re-named the BUILD grant. For more information visit the USDOT's website. https://www.transportation.gov/BUILDgrants

The BUILD program, previously known as the and Transportation Investment Generating Economic Recovery (TIGER) discretionary grants, was established under the American Recovery and Reinvestment Act of 2009 and operated under annual appropriations acts until authorized in November 2021.

Project Funding Breakdown 
Total Planning Project Cost$2,318,235 
Total RAISE Federal Funding$2,086,412 
Total 10% City Match$231,823 

Community Meetings:

Community engagement meetings will be held throughout the project, starting in early 2026.

Project Documents and Images:

Questions and Answers:

Q: What is the LINC Norfolk project and why is it important?

A: LINC Norfolk stands for Local Intermodal Network Connection. It’s a planned 4.8-mile, 10-foot-wide multi-modal path that will create a continuous connection from Skyview Park on the northwest side of town to the Cowboy Trailhead and Ta-Ha-Zouka Park on the southeast side — running through the heart of Norfolk.

The project also includes infrastructure upgrades along the route, including street reconstruction and long-needed drainage improvements on Northwestern Avenue and 7th Street. Additional landscaping, lighting, and streetscape enhancements will help revitalize the historic South Norfolk area.

LINC is funded by a $2.3 million federal RAISE grant from USDOT and the Federal Highway Administration, with a 10% local cost share.

This project will reconnect neighborhoods south of Highway 275 — giving children a safe route to school and parks, providing people without cars a reliable way to get to work or services, and offering everyone more opportunities to walk and bike. It will serve as a backbone route for expanding Norfolk’s trail network in future projects.

Q: How has the community been involved in shaping the LINC Norfolk project?
A: Community input has guided this project from the start. Residents and business owners in South Norfolk have long called for revitalizing Northwestern Avenue and the old stockyards area. More recently, through outreach for the city’s Multimodal Transportation Action Plan, more than 440 residents emphasized three priorities:

  • Safer crossings and sidewalks
  • Better trail connectivity to schools, jobs, and daily destinations
  • More transportation choices beyond driving

This echoed the 2019 Bicycling and Walking Plan, which prioritized dedicated bike space, improved safety, and safe walking routes, and the new Parks and Recreation Master Plan, which identified trail connectivity as a top need.

LINC Norfolk directly responds to this feedback by building the safe, connected network residents have asked for.

Q: How will it improve safety in Norfolk?

A: Safety is a top priority, as emphasized in the City’s Multimodal Transportation Action Plan to eliminate pedestrian and traffic-related deaths and serious injuries.

Today, many pedestrians must walk in the street or on narrow, broken sidewalks with few safe crossings. LINC will provide a fully separated path, ADA-compliant curb ramps at all intersections, a tunnel under Highway 81 to eliminate at-grade highway crossings, and a pedestrian refuge island at Highway 275.

These improvements will dramatically reduce the risk of pedestrian crashes and make active transportation safer and more comfortable for everyone.

 
Q: How will this project impact quality of life and the local economy?

A: LINC will strengthen Norfolk’s entire transportation network. It will connect seven parks, eight schools, downtown’s business and entertainment district, and the city’s social services hub — making it easier and safer to get around without a car.

It also links directly into the Cowboy Trail, part of the 3,700-mile Great American Rail Trail, which will bring more regional and national visitors into Norfolk for events like the Cowboy 200. This increased activity will support local restaurants, shops, and events.

High-quality trails like this have been shown to increase physical activity, improve public health, and foster stronger community connections. They also make communities more attractive to residents, visitors, and employers.

Norfolk has seen this with the revitalization of Johnson Park and the North Fork Whitewater Park, which helped spur private investment downtown. LINC will extend that success into historically disadvantaged neighborhoods like South Norfolk — bringing visible improvements, new destinations, and new investment.

As urbanist Richard Florida notes, when cities invest in placemaking, they create places where people want to live, work, and start businesses. LINC Norfolk will be a catalyst for that kind of growth.

 
Q: What’s next for the project?

A: The City has an agreement with NDOT to launch the planning phase and issue RFQs for design consultants.

The selected consultant will lead extensive public engagement, explore design alternatives, and produce 60% design plans. This process will begin within the next month and is expected to wrap up by late 2028.

At that point, the project will be grant-ready for construction funding — with strong design work, early permitting, and broad community support in place.

LINC Norfolk will create a safe, connected, and vibrant trail that improves mobility, health, and opportunity for everyone in Norfolk.

Contact for Further Information:

Steven Rames
Public Works Director & City Engineer
402-844-2020